Project
Breakdown
Project
Scope
This contract involved the internal refurbishment of 65 Units spread over three different Courts. The works included the removal of existing finishes ( wall paper, floor coverings etc), and the installation of new kitchen, wardrobes and vanity units, construction of new partitions, new floor coverings, and re-decoration of the units, both externally and internally. The project was handled in phases, and required that work were completed to strict timeframes as the movement of tenants were scheduled months in advance. The work also involved liaising, not only with Council Projects team, but also with the tenancy department.
Project
Highlights
Project Manager
David Stanford, Manukau City Council
Architects
Catalyst Consulting
Programme
48 Weeks
Completion
March-2010
Client
Client
Manukau City Council
Project
Gallery
Similar
Projects
Start Your Project
Get your upcoming project off to a great start by tapping into our extensive expertise. Reach out to us today and let’s begin.